Wise County microreactor study: no county tax dollars, officials say, as residents demand trust first
Wise County officials made one promise clear at a public meeting on a possible future microreactor: local taxpayers will not foot the bill. Brian Falin, director of the county's Industrial Development Authority, said Thursday, Nov. 5, that any future nuclear or new energy project would not be funded with county dollars, according to Cardinal News, and that his priority is building a commercial tax base.
The meeting at the Inn at Wise previewed a $100,000 microreactor feasibility study, funded by the GO Virginia Region 1 Council and led by the Virginia Innovative Nuclear Hub. The final report is due in December and will be released to the public.
Jobs on one side, trust on the other
Residents who took part in two surveys, which drew almost 500 responses, and two input sessions in May ranked employment and economic development as the biggest potential benefits, along with tax revenue and more affordable energy for families and businesses. They want those benefits to stay local, including lasting jobs.
But the same feedback showed caution. About half of respondents said they do not support nuclear energy, said Jeff Whitt, executive director of the nuclear hub. There was little appetite for sending future power to data centers, and trust was low across the board in local government, state government and developers.
Residents also told the study team what it would take to change minds. According to the surveys, protecting local water resources, more public involvement and a satisfactory plan for nuclear waste would help win over some of those now opposed. Transparency in decision-making and real chances for public participation ranked near the top of residents' concerns.
About 25 people came to Thursday's presentation, where Whitt and Falin took questions after reviewing the results.
"Not here" yet
Falin pushed back on the idea that a reactor is coming soon. "These projects are not here. We are trying to prepare for the projects to be here," he said. The study has not looked at a specific site. It will instead guide the county on energy demand, siting, costs, economic impact and community fit, and will also weigh wind and solar.
Microreactors could produce up to 20 megawatts of thermal energy, and none has been built in the U.S. yet. Falin said rugged terrain and old mine land limit where development could go, and that power would likely be exported because local demand is small.
Wally Smith, a UVA Wise biology professor on the study's advisory committee, said the original regional rollout "was really done backwards," and that the county is "now doing what should have been done four years ago."
For a coalfield county weighing its energy future, the takeaway is that any energy future will have to earn residents' trust first and keep the risk off the local taxpayer.
Wise County is a county in Southwest Virginia. Its county seat is Wise.
Wise County GO Virginia microreactor nuclear energy Southwest Virginia Virginia Innovative Nuclear Hub Wise County